Licensing / Application Detail
LIC-2024-0891 — PT PLN (Persero)
Under Review
Electricity Generation · 500 MW · East Java
Submitted: 12 Mar 2024
Application Summary
| Application ID | LIC-2024-0891 |
| License Type | Electricity Generation |
| Sector | Electricity |
| Sub-type | Combined Cycle Gas Turbine (CCGT) |
| Installed Capacity | 500 MW |
| Operation Province | East Java |
| Operation City | Surabaya, Sidoarjo, Gresik |
| License Duration | 10 Years |
| Intended Start Date | 1 July 2024 |
| Commercial Op. Date | 30 June 2026 |
Processing Status
| Current Status | Under Review |
| Review Stage | Technical Review |
| Assigned Officer | Budi Santoso (Technical) |
| Secondary Officer | Reza Pratama (Financial) |
| Date Submitted | 12 March 2024 |
| Days in Review | 43 days |
| Target Decision Date | 30 April 2024 |
| Application Fee | IDR 25,000,000 |
| Payment Status | Paid |
| Payment Date | 14 March 2024 |
Review Checklist Progress
Initial Screening
Completed
15 Mar 2024
Document Verification
Completed
22 Mar 2024
Technical Review
In Progress
Since 1 Apr 2024
Financial Review
Pending
—
Legal Review
Pending
—
Commissioner Decision
Pending
—
Actions
Key Dates
Submitted12 Mar 2024
Payment14 Mar 2024
Target Decision30 Apr 2024
Days Elapsed43 days
Days Remaining17 days
Assigned Officers
BS
Budi Santoso
Technical Review
RP
Reza Pratama
Financial Review